Jan. 2008 - June 2010
Facility Management

Electrical work:

  • Supply and installation of Medium voltage SWGR, transformer cable and duct bank.

Mechanical work:

  • Supply and installation of diesel generator with weather proof enclosure, fuel tank, fuel system.
  • Fuel loading and unloading for main tanks 1000M3.
  • Connecting the two main tanks with fuel system for generator and firefighting system.
  • Make the extension of fire fighting system.